installation manual furnace gua120a020

The GUA120A020 furnace is a high-efficiency residential heating system with 120,000 BTU capacity, featuring electronic ignition, variable-speed blower motor, multi-speed operation, and compatibility with various thermostat systems. Designed for forced-air applications with AFUE ratings up to 96%, this natural gas furnace includes safety controls, diagnostic LED indicators, and requires professional installation. Below are essential sections covering safety precautions, installation procedures, setup guidelines, specifications, and troubleshooting.

1. Safety Precautions 2. Pre-Installation Requirements 3. Installation Procedures 4. Electrical Connections 5. Gas Line Connections 6. Venting System Installation 7. Startup and Commissioning 8. Specifications 9. Control Settings 10. Maintenance Guidelines 11. Troubleshooting

Safety Precautions

Critical safety measures must be followed during installation and operation.

HazardPrecaution
Gas LeaksCheck all connections with leak detection solution; never use open flame
Electrical ShockDisconnect power before servicing; ensure proper grounding
Carbon MonoxideInstall CO detectors; ensure proper venting
Fire HazardMaintain clearance from combustibles; install smoke detectors
Burn RiskAllow unit to cool before servicing; wear protective equipment

Pre-Installation Requirements

Site preparation and verification before installation.

  1. Location: Indoor installation only; minimum clearances: 1" sides, 6" front, 24" top.
  2. Foundation: Level, solid concrete or approved masonry base.
  3. Combustion Air: Verify adequate fresh air supply per local codes.
  4. Gas Supply: Confirm natural gas availability; pressure 6-7 inches WC.
  5. Electrical: 120V, 60Hz dedicated circuit; proper grounding required.

WARNING! Installation must comply with all local codes and regulations. Professional installation required.

Installation Procedures

Step-by-step furnace installation process.

  1. Position furnace: Place on level foundation in approved location.
  2. Ductwork connection: Install supply and return ducts; seal all joints.
  3. Remove shipping materials: Remove all protective covers and shipping restraints.
  4. Filter installation: Install approved air filter in filter rack.
  5. Condensate drain: Connect PVC drain line to condensate trap.

CAUTION! Furnace is heavy; use proper lifting equipment and techniques.

Electrical Connections

WARNING! Disconnect power before making electrical connections.

Gas Line Connections

Natural gas piping and connection requirements.

  1. Gas pipe sizing: Minimum 3/4" black iron pipe for entire run
  2. Shutoff valve: Install approved gas shutoff valve within 6 feet
  3. Drip leg: Install sediment trap before gas valve connection
  4. Pressure test: Test at 14" WC for 10 minutes; no pressure drop
  5. Leak check: Use leak detection solution on all connections

DANGER! Gas leaks can cause explosion or fire. Test thoroughly.

Venting System Installation

Category IV venting requirements for high-efficiency furnace.

ComponentRequirement
Vent MaterialPVC or CPVC Schedule 40
Vent Size2" or 3" diameter per installation manual
Vent Slope1/4" per foot toward furnace
Clearances1" from combustible materials
Termination12" minimum above grade/snow line

Startup and Commissioning

Initial startup procedure and system verification.

  1. Power on: Restore electrical power to furnace
  2. Gas supply: Open main gas valve and appliance shutoff valve
  3. Thermostat: Set to heating mode; raise temperature above room temp
  4. Sequence verification: Observe ignition sequence and flame establishment
  5. Temperature rise: Measure temperature rise; adjust blower speed if needed
  6. Combustion analysis: Verify CO levels and combustion efficiency

Specifications

Control Settings

Furnace control board settings and adjustments.

DIP Switch Settings: Blower speeds (COOL, HEAT), Fan ON delay, Fan OFF delay

Diagnostic LEDs: Flash codes for normal operation and fault conditions

Gas Valve: Factory set pressure; do not adjust unless qualified

Limit Switches: Auto-reset rollout and high limit protection

Maintenance Guidelines

Routine maintenance requirements for optimal performance.

  1. Monthly: Check air filter; replace when dirty
  2. Annual: Professional inspection and cleaning
  3. Blower assembly: Clean annually; check motor amperage
  4. Heat exchanger: Visual inspection for cracks or damage
  5. Vent system: Inspect for obstructions or damage
  6. Drain system: Clean condensate trap and drain lines

Troubleshooting

SymptomPossible CauseCorrective Action
No heatPower, thermostat, gas supplyCheck circuit breaker, thermostat setting, gas valve position
Furnace won't startDoor switch, limit controlEnsure door properly closed; reset rollout switch if tripped
Short cyclingDirty filter, airflow restrictionReplace filter; check for blocked vents or registers
Blower runs continuouslyThermostat fan settingCheck thermostat fan setting (AUTO/ON); faulty fan relay
Ignition failureGas supply, igniter, pressure switchVerify gas pressure; check igniter for cracks; clear vent obstruction

Service: Contact qualified HVAC technician for complex issues

Warranty: Limited lifetime heat exchanger; 10 years parts